Blakes Hotel, Shoreditch
11-storey Hotel Development with 4-storey Basement within a Constrained Urban Site

Sector
Hotels
Service
Civil & Structural Engineering
Completion
2023
Project Value
£32M
Location
London
Client
17 Corsham Street Ltd
Architect
Maith Design
Contractor
RGB Group
Project Details
Our original design for the scheme, to meet the Employers Requirements, was a full insitu reinforced concrete frame. As the construction was coming out of the ground and as we reached the milestone of ground floor construction slab level with the concrete core up to 6th floor, the clients Employers Agent requested a review of the building to determine if additional storeys could be added. Due to the significant value engineering exercise, we undertook of the basement construction with the piling subcontractor and with minimising the carbon footprint of the building by minimising material usage through efficient and rationalised design, thus, leaving minimal scope for extension. As such, a full redesign was undertaken at the instruction of the client to achieve additional storeys, where we concluded with a hybrid structure.
The development is located on a tight site that is bound by highways and neighbouring buildings. Shear Design were responsible for co-ordinating detailed ground investigations and reporting to allow the design to proceed.
Shear Design coordinated the Approval in Principle submissions for the basement retaining walls which were CAT 3 structures due to their retained height, as such, subject to 3rd party checks.
Due to funding requirements, the entire building design was subject to 3rd party engineer check of all the professional services, including civil and structural engineering services. We worked with the checking engineer, resulting in full sign off, of our design.
Services
Full civil and structural engineering design
Hybrid structural frame design
Reinforced concrete core design
Structural steelwork frame design
4-storey basement structural design
Piled foundation design
Party wall interaction assessment
Coordination with architect, contractor, and wider design team